Speed


Using IJM Fastrak system your building time can be reduced by up to 50% with a lot less requirement for on-site management, plant and labour providing substantial overhead cost reduction.


Construction Sequence


Standard Masonry Construction

Weeks

IJM FasTrack

Foundations

1

Foundations

Foundations

2

Foundations

Bricklayer ground floor

3

Erect timber frame structure, fix & glaze windows

Bricklayer

4

Felt, battens, tile roof

Fix & glaze windows

5

Brickwork & first fix

6

Roof structure

7

Insulate

Felt, battens, tile roof

8

Dry line

First fix

9

Second fix

Plasterwork

10

Decorate and move in

Plasterwork

11

 

Average building time can be substantially reduced using IJM FasTrak system with significant reductions of on site labour.

12

Second fix, plumber, electrician

13

14

15

16

17

Second fix, carpenter

18

...

19

Decorate, move in

20

 





TIMBER FRAME WITH CONFIDENCE


If you have a question or enquiry, please contact us at sales@ijmtimberframe.com and we will always be delighted to help!

With our wide range of experience and knowledge, IJM are happy to design and build any timber products you may desire


EMAIL US TODAY